海油工程-外输计量撬及电缆托架等

海油工程-外输计量撬及电缆托架等

发布于 2025-08-01

招标详情

海洋石油工程股份有限公司
联系人联系人622个

立即查看

可引荐人脉可引荐人脉639人

立即引荐

历史招中标信息历史招中标信息26767条

立即监控

中国海油供应商**开发公开征集公示

中国海油因生产建设工作需要,诚邀具备研发能力、制造能力和相关业绩的国内优秀供应商,与中国海油共同开展工作。现将相关信息公开如下:

1.需求概况

一、产品:Fuel Gas Metering

技术要求:Flowmeter shall be Coriolis meter type with differential pressure measurement and pressure and temperature compensation.

1*100%; 2" 300LB RF, design temperature 150℃, design pressure 45barg; design flowrate 5.4 MMSCFD; Output: 4~20mA and Modbus TCP; NACE MR0175/ISO 15156; Painting Coating: ISO12944 CX; Lightning Surge Protection; EMI/RFI Immunity: Level B of IEC 61000-6-2; Zone 1, Class IIB, T4; IP66; Accuracy ±0.2%;

Flange and wetted part: Hastalloy C

二、产品:GASLIFT METERING PACKAGE

技术要求:Flowmeter shall be Coriolis meter type with differential pressure measurement and pressure and temperature compensation.

1*100%; 2" 1500LB RF, design temperature 150℃, design pressure 192.5barg; design flowrate 8 MMSCFD; Output: 4~20mA and Modbus TCP; NACE MR0175/ISO 15156; Painting Coating: ISO12944 CX; Lightning Surge Protection; EMI/RFI Immunity: Level B of IEC 61000-6-2; Zone 1, Class IIB, T4; IP66; Accuracy ±0.2%;

Flange and wetted part: Hastalloy C

三、产品:EXPORT LIQUID FISCAL METERING PACKAGE

技术要求:Flowmeter shall be Coriolis meter type.

2*100% (A-02701A/B); 8" 300LB RF, design temperature 150℃, design pressure 46.6barg; design flowrate 30 kbpd; Output: 4~20mA and Modbus TCP; NACE MR0175/ISO 15156; Painting Coating: ISO12944 CX; Lightning Surge Protection; EMI/RFI Immunity: Level B of IEC 61000-6-2; Zone 1, Class IIB, T4; IP66; Accuracy ±0.1%;

Flange and wetted part: Hastalloy C

四、产品:GAS FISCAL METERING PACKAGE

技术要求:The gas fiscal metering package (A-03701) consists of:

● 2 x 100% metering runs (1 duty, 1 standby), each utilizing an coriolis meter;

● 1 automatic sampler;

● 2 redundant gas chromatographs, with carrier gas and calibration gas bottles;

● 1 relative density meter;

Note: A mobile prover shall be used for proving the meters and/or they shall be proven at an onshore calibration facility.

The gas fiscal metering system will be a stand-alone system which will be able to operate independently from the Control System, but it will be interfaced with the Process Automation System (PAS) to such a degree that all day-to-day operations may be carried out through an Operator Workstation OWS in the CCR.

Inlet/Outlet 14" 1500LB, design temperature 150℃, design pressure 225.4barg; ; design flowrate 250 MMSCFD; NACE MR0175/ISO 15156; Painting Coating: ISO12944 CX; Lightning Surge Protection; EMI/RFI Immunity: Level B of IEC 61000-6-2; Zone 1, Class IIB, T4; IP66; Accuracy ±0.1%;

Flange and wetted part: Hastalloy C

五、产品:Channel

技术要求:316L 30M 3m/根 T:2.0 X:68 Y:50 Z:50 L:3000 A: 11*35 CC: 50

六、产品:Channel

技术要求:316L 30M 3m/根 T:2.0 X:138 Y:100 Z:100 L:3000 A: 11*35 CC: 50

七、产品:Locking Bolt set

技术要求:316L 700个 L:25 D1:24 DT :10 S:2.8 NECK SIZE LOW NECK LT1:22.2 TORQUE(Nm)4.-45

八、产品:Edge Protector

技术要求:100个 Rubber T:7.0 X:95 Y:6.5 Z:49 HOLE SIZE:81*35 S 2.0

八、产品:Base

技术要求: 316L T:4.0 T1:5.0 X:65 Y:150 Z:65 A HOLE SIZE:11*35 B HOLE SIZE:11*11 CC:150 CC1:100 CC2:58 CC3:50 DIA:200

九、产品:Base

技术要求:316L T:5.0 X:200 Y:130 Z:200 A HOLE SIZE:13*25 B HOLE SIZE:11*20 CC:50 CC1:150 CC2:150 CC3:25 CC4:50 CC5:100 FLANGE:25 SPACING

2.对供应商的要求

一、供应商应为制造商。

二、具有相应的生产资质要求和质量管理体系证书。

3.项目联系人

请感兴趣的供应商于2025年8月8日前,与我方联系人接洽。

联系人:徐辉

电 话:155****点击查看0620

邮 箱:ex_xuhui5@cooec.****点击查看.cn

(****点击查看

2025年7月30日

关键词